Plan Your Spring Building Project Now

Planning ahead is key when it comes to starting spring building projects. If you’re considering a new shop, farm building, storage space, or hangar in 2024, now is the time to get started.


 

Farrow Built Black Shop

Here’s how our process works and why early planning makes a difference:


1️⃣ Engineered Plans: Once you book your project, it takes about a month to finalize engineered plans.

2️⃣ Permits: After plans are ready, we’ll submit for your building permit. Permit approvals generally take 1–2 months.

3️⃣ Start Date: We guarantee a start date within six weeks of permit approval.


 

What does this timeline mean for your project?

  • Book now → Engineered plans by the end of December

  • Permits approved → End of January or February

  • Build start → Late March, April, or May, depending on permit timing.


If you want to break ground in spring and enjoy your new building by summer, now is the best time to plan your spring building project. Our schedule fills up fast, so don’t wait to secure your spot.


 

Contact us today to discuss your vision and start the process. Let’s make 2024 the year your dream building becomes a reality!

2 views0 comments

Recent Posts

See All

Comments


  • Farrow Built YouTube
  • Farrow Built Facebook
  • Farrow Built Instagram
  • Farrow Built Linked In
  • Farrow Built Tik Tok
bottom of page